![]() |
|
![]() | ||
|
Subject:
CONTRACT LAW QUESTION: SERVICES RENDERED, PAYMENT DENIED. ($30.00)
Category: Reference, Education and News > General Reference Asked by: another-ga List Price: $30.00 |
Posted:
30 May 2004 17:09 PDT
Expires: 29 Jun 2004 17:09 PDT Question ID: 354035 |
Grandscale Developers plan to build a condominium community in the Blue Zone Mountain area. Part of the plans includes constructing a pool at the foot of a hillside. Grandscale contracts with Priceright Construction Company to dig a tunnel through the mountain for access to the site of the proposed pool. The contract is based upon an estimate that calls for removal of 600,000 cubic yards of dirt. When Priceright begins the job it is discovered that the inner portion of the mountain is composed completely of shale and the job will now require $50,000 of additional expenses to complete. Grandscale agrees to Priceright?s demand for additional compensation. Later Priceright?s demand for payment is refused and Priceright brings a lawsuit on the promise to pay the additional $50,000. How might the Court rule on Priceright?s request for payment of the additional $50,000 and why? ***CONTRACT LAW*** | |
| |
|
![]() | ||
|
There is no answer at this time. |
![]() | ||
|
Subject:
Re: CONTRACT LAW QUESTION: SERVICES RENDERED, PAYMENT DENIED. ($30.00)
From: neilzero-ga on 31 May 2004 17:18 PDT |
Since the additional payment was agreed to, this is an amendment to the original contract, therefore Priceright is entitled to $50,000 in additional payment. There could however be exceptions, such as priceright has a reputation for asking for more money to complete jobs. Priceright lied significantly about the additional cost caused by the shale. Priceright knew about the shale and premeditated asking for more money using the shale as an excuse. Intimidation was envolved, such as the job would be abandoned by Priceright unless the price increase was approved.The person who agreed to the additional $50,000 was not authorised by Grandscale, or said person denighs that they agreed on behalf of Grandscale. Bribes were given and accepted. Clauses in the original contract, and the amendment, if the latter was done in deyail and in writing. Local precidents establihed in similar cases. Other contractors bid about the same dollars on the job, but Priceright got the job because they promised there would be no cost over runs. There are lots of possibilities for exceptions, IMHO. Neil |
Subject:
Re: CONTRACT LAW QUESTION: SERVICES RENDERED, PAYMENT DENIED. ($30.00)
From: ipfan-ga on 01 Jun 2004 12:11 PDT |
A key fact is needed: when you say that Grandscale ?agreed? to Priceright's demand for compensation, how exactly did they agree? Ninety-nine percent of construction contracts contain provisions dealing with change orders (which is nothing more than an amendment to the original scope of performance and price), and the general rule is that change orders must be in writing signed by authorized representatives of both parties. In other words, if Priceright's construction superintendent spoke to Grandscale's receptionist on the phone and the receptionist (who has no signature authority) said, "Sure, go ahead," then Priceright may have problems collecting if the original contract requires a written, authorized change order. Two legal theories may change that result: even assuming the change was not authorized, Priceright can bring a claim under a doctrine known as quantum meruit. It is an equitable theory that holds that even if a formal contract (here, change order) does not exist between the parties, if Priceright performed in reasonable reliance on Grandscale's permission (even if not authorized), then Priceright should be paid the reasonable value of the service rendered because if not, then Grandscale will be unjustly enriched to the tune of $50,000. The second theory that Priceright may rely upon is that of apparent authority. If the Grandscale receptionist (in my hypothetical) represented to Priceright that he or she was in fact authorized to bind the company contractually and if Priceright's reliance on that representation was reasonable, then the Grandscale receptionist had "apparent authority," and Priceright may be entitled to rely on that to form a binding contract (change order). Thus, we have at least two independent theories under which Priceright may sue and win even absent a signed change order: quantum meruit and apparent authority. If, on the other hand, the ?agreement? referenced in your fact pattern was an actual, written, authorized change order, the Priceright should win in any event. |
If you feel that you have found inappropriate content, please let us know by emailing us at answers-support@google.com with the question ID listed above. Thank you. |
Search Google Answers for |
Google Home - Answers FAQ - Terms of Service - Privacy Policy |