Clarification of Question by
wasiq-ga
on
26 Aug 2004 11:11 PDT
Thanks for your interest in this problem. I shall try to clarify all
of the issues that you have mentioned in your comment in the order
they were posted.
1. Normally the factory works in two shifts per day, but during the
peak production days, the factory may be required to do a third shift
as well. At this moment we shall consider 2 shifts only.
2. Again, the working week is of 5 days, but on peak production, the
factory may be required to operate all seven days. But right now we
are assuming a 5 day week.
3. Machine operation duration is in minutes beacause of the fact that
even the smallest of the operation takes more than a minute. Even your
consideration of seconds as the duration would pose no problems as I
can convert that on my own, but please be careful that whatever unit
of duration you choose should be consistent throughtout the solution
of the problem.
Units can be items processed per hour. Again I can convert that to
other measurements on my own if the need arises.
4. There is no travel time between the machines, they are located
pretty close to each other.
5. Yes, initial start state is a clear line.
6. I really did'nt get your question this time around. What do you
mean by initial configuration of machines?
7. Yes, it can be either, depending on the availability. As a rule of
thumb, if all machines for an operation are available then the most
efficient one should be used.
8. Yes, all machines for an operation can be used at the same time.
9. Yes, its OK to complete a shift mid cycle with no down time.
10. No there is no limit to the number of items that can queued. This
is actually a major concern for me as some process being slow becomes
the bottleneck operation, therefore the number of completed items
cannot be greater than the bottlneck operation.
Thanks again for your interest. I am available for for queries.
Regards
Wasiq